Based on P&U experience we were able to suggest changes to the proposed design which had positive impacts on the time and budget.

ClientSouthern Sydney Freightline
IndustrySubstation
Value$300,000
Date2010 - 2012

Scope

This project was required for a new dual carriageway to Campbelltown to cater for increased freight train traffic
Work on this project included:

  • Installation of a new compressor hut for Southern Sydney Freightline.
  • Installation of a new 315 kVA pole transformer to upgrade the existing high voltage to increase the power load of the low voltage network.
  • Back up supply.
  • Endeavour Energy pole mounted transformer for security of supply for rail network.

The P&U Difference

P&U’s ability to handle both the overhead and underground portions of the project made the job easy for the client to manage, i.e. a single contractor and no need for subcontractors.